Mark ceiling levels carefully. Take into consideration the thickness of Gypsum board & install the perimeter wall angles.
Mark the position of eyelet pins on the ceiling, making sure that the 'C'
channel at wall ends, is not more than 300 to 450 mm away from the wall. Install Eyelet
pins/cleats by automatic guns.
Install hanger rods, adjustable clips &
channel brackets.
Install 'C' Channels @ 1200 center to center.
Install Furring Channel at 600 MM center to
center &secure it by installing wire connecting
clip to hold the 'c' channel and furring channel
together.
Fix the wire connecting clip to hold the 'C'
channel and furring channel together.
Install the Gypsum board from below with the help of screw guns and good
quality drywall screws.
Note for specific applications supports should be designed suitably.
|